Project supply and installation / Illustrative case study
COREVA ERP: Purchasing and Project Cost Control
Follow a project purchase from budget approval to partial receipt and invoicing while keeping commitments separate from actual costs.
COREVA ERP ↗
PROJECT BRIEF
The business behind the requirements.
Key participants: Project managers, procurement, warehouse receiving and finance controllers.
The pilot assumes equipment is purchased for specific installation projects and sometimes delivered in stages. Scope includes project allocation, commitments and receipt-to-invoice reconciliation. Complex scheduling and subcontractor payroll remain outside the initial implementation. The team first agrees how cost is recognized in each project report.
01 / THE CONTEXT
Where the friction starts.
An illustrative installation business buys equipment for customer projects. Project managers see invoices only after purchasing commitments have already been made. Partial deliveries and substitutions make it difficult to know whether a project is within budget or simply waiting for supplier invoices.
The constraint that shapes the solution
Committed cost and actual cost must remain distinct. A late invoice cannot be treated as new budget consumption if the corresponding receipt or commitment is already represented.
02 / DESIGN DECISIONS
The proposed COREVA approach.
Each decision addresses a specific failure mode in this scenario.
Associate each purchase request and order line with an approved project and cost category.
Model ordered, received and invoiced quantities separately, including approved substitutions and partial receipts.
Define reporting treatment for commitments and actuals with finance so management reports avoid double counting.
THE WORKFLOW IN PRACTICE
Follow the work through the system.
Approve a project requirement
A purchase request carries the project, cost category and business reason. Budget review happens before the order creates a commitment.
Record partial delivery
Receiving records what actually arrived and raises discrepancies for substitutions or shortages. Outstanding quantities remain visible.
Reconcile cost
Finance reviews the invoice against the order and receipt. Reports distinguish remaining commitments from actual costs without summing the same value twice.
03 / DELIVERY PLAN
Build confidence before expanding scope.
- PHASE 01
Agree a project cost model using representative equipment purchases and supplier invoices.
- PHASE 02
Configure approval authority and rehearse receipt discrepancies, cancellation and credit-note handling.
- PHASE 03
Pilot one project portfolio and reconcile open commitments before adding historical projects.
RISK & RELEASE READINESS
What must be resolved before release.
Unit conversions, supplier substitutions and backdated invoices can distort project costs. Those cases need explicit rules rather than manual spreadsheet fixes outside the ERP.
Acceptance checks
Run a full order, a partial receipt, a cancelled balance and a credit note through project reporting. Finance must reconcile each state to its supporting transactions before acceptance.
Handover & ownership
Deliver cost-category mappings, approval rules, receipt exceptions and reconciliation instructions. Project owners review commitments; finance owns accounting definitions and closing treatment.
04 / SUCCESS CRITERIA
How we would evaluate the work.
These are proposed measures, not achieved results. Baselines, targets and observation periods would be agreed during discovery.
- Review purchase lines missing valid project allocation.
- Track discrepancies between ordered, received and invoiced quantities.
- Measure unexplained differences between project reports and approved financial records.
05 / THE TAKEAWAY
What this scenario teaches
Project control begins when a commitment is made. Connecting purchasing and finance helps teams distinguish money already committed from costs that have actually been recognized.
Explore COREVA ERP ↗LET’S APPLY THIS TO YOUR CONTEXT
Similar challenge.
Different business?
Tell us what is happening today and what needs to change. We’ll help shape the scope around your operations.
Talk to COREVA ↗KEEP EXPLORING